Posted on: October 20, 2017

October 20: Morgan Territory Road Repair Project Update

During the last week, the County’s contractor completed the earthwork between the retaining walls. This work included installation of subsurface drainage. The installation of the new 8” waterline is anticipated to be completed by Octob...

Read on...

Morgan Territory Road Updates
Posted on: October 13, 2017

October 13: Morgan Territory Road Repair Project Update

The County’s contractor for the Morgan Territory Road Slide Repair project is making good progress with the earthwork operation between the two retaining walls. The earthwork began on October 5 and includes excavation of the earth between the tw...

Read on...

Morgan Territory Road Updates
Posted on: October 6, 2017

October 6: Morgan Territory Road Slide Repair Project Update

The contractor poured the concrete cap beam for the downhill retaining wall this week. The reinforced concrete cap beam is a 4'x4'x250' structural element that sets the top of the downhill retaining wall. The contractor also began installation of drainage...

Read on...

Morgan Territory Road Updates
Posted on: September 29, 2017

September 29: Morgan Territory Road Slide Repair Project Update

This week the contractor completed drilling the foundation piles for the downslope retaining wall. The downhill retaining wall includes the installation of 36 inch diameter cast-in-drilled-hole reinforced concrete piles to depth of approximately 57 feet (...

Read on...

Morgan Territory Road Updates
Posted on: September 22, 2017

September 22: Morgan Territory Road Repair Project Update

Repair Project:

We received several questions about the repair project that we want to clarify.

The new road width will have 27.5 feet of pavement between the concrete railings. The previous paved width was approximately 20 feet.

We expect that the retaining...

Read on...

Morgan Territory Road Updates
Posted on: September 20, 2017

September 20: Morgan Territory Road Repair Project Schedule Update

The project schedule has been revised for project completion in mid-November. The schedule revision is due to several factors. More rock was encountered during the pile drilling operations than anticipated and additional drainage improvements are being in...

Read on...

Morgan Territory Road Updates
Posted on: September 15, 2017

September 15: Morgan Territory Road Repair Project Update

Last week, the contractor completed installation of the soil anchors at the uphill retaining wall. This week the work shifted to the construction of the downhill stitch pile retaining wall. The downhill retaining wall includes the installation of 36-inch ...

Read on...

Morgan Territory Road Updates
Posted on: September 7, 2017

September 7, 2017: Morgan Territory Road Repair Project Update

This past week, the contractor completed the drilling operation for the horizontal soil anchors (total 30) at the uphill retaining wall. The work involved drilling a 6 inch diameter hole extending approximately 60 feet from the face of the retaining wall....

Read on...

Morgan Territory Road Updates
Posted on: August 29, 2017

August 29: Morgan Territory Slide Repair Project Update

The slide repair project continues to move forward on schedule with completion projected in mid-October. This past week the County's contractor installed most of the concrete lagging between the soldier piles forming the face of the uphill retaining wall....

Read on...

Morgan Territory Road Updates
Posted on: August 23, 2017

August 23: Morgan Territory Slide Repair Project Update

The slide repair project continues to move forward on schedule with completion in mid-October. The County's contractor completed installation of the 32 soldier steel piles which are the foundation for the uphill retaining wall. The pictures below show the...

Read on...

Morgan Territory Road Updates
Posted on: July 21, 2017

July 21: Temporary Access Road Reminder

Please keep your speed to 15 miles per hour on the temporary access road. Your neighbors on Leon Drive have allowed the use of their private road for this access so it’s important to keep speeds to the posted speed limit. The County will need to...

Read on...

Morgan Territory Road Updates
Posted on: July 14, 2017

July 14: Morgan Territory Road Closure begins Monday, July 17 at 7:00am

The Morgan Territory Road Slide Repair project will begin on July 17. Morgan Territory Road will be fully closed to vehicles, cyclists and pedestrians beginning at 7:00 a.m. on July 17 and extending through mid-October. During the approximately 3-month lo...

Read on...

Morgan Territory Road Updates
Posted on: July 6, 2017

July 6: Morgan Territory Road Repair Project/AT&T Work

Morgan Territory Road Slide Repair Project

The Morgan Territory Road Slide Repair project is scheduled to begin on July 17th. Morgan Territory Road will be fully closed to vehicles, cyclists and pedestrians at 7:00 a.m. on July 17th and the temporary acces...

Read on...

Morgan Territory Road Updates
Posted on: June 29, 2017

June 29: Temporary Access Road Passes

The Morgan Territory Slide Repair project is scheduled to begin in July. We will notify you of the project start date. During construction Morgan Territory Road will be closed and the temporary access road will be open.

The County is issuing temporary acce...

Read on...

Morgan Territory Road Updates